Construction Of Runway, Taxiway And New Apron At Sinop Airport
Employer
General Directorate Of State Airports Authority
Project Content
- Deplacement of Karasu Brook with 415 m3/sec flow rate to construct runway onto old stream bed.
- Runway : 2200 m x 45 m concrete pavement, starting from +2m evelation and ending at +6,50m elevation, including all infrastructure .
- AGL (Airport Ground Lightning) jobs including: Installation of Runway edge, taxiway edge, approach, flash lightning systems and PAPI with central control system.
- Total duration of job was 550 days but it was completed 7 months before the deadline